East Ranch Community Park Public Restroom Building Installation Project
Posted – Sept 12, 2024, Closes - October 4, 2024
The Cambria Community Services District is requesting formal, sealed bids from licensed contractors for the installation of a prefabricated restroom building, associated building utilities, and a concrete walkway.
9/20/2024: Addendum Number 1 to the Bid Documents for the installation of a prefabricated restroom building, associated building utilities, and a concrete walkway are posted below.
The full request package can be accessed below.
Notice to BiddersPublic Works ContractExhibit A - Bid Proposal FormExhibit B - Project DescriptionExhibit C - Construction Mitigation MeasuresExhibit D - Stamped PlansExhibit E - Soils ReportExhibit F - Soils Review LetterAddendum(s)
Any addendums will be added here during the open period of this RFP. Please sign and submit with the Bid Proposal Form any addendums that are added.
Addendum Number 1 to the Bid DocumentsSubmittal Procedures and Deadline
Formal Bids will be received until October 4, 2024, at 10:00 am.
Bids are to be delivered sealed to the District’s Wastewater Treatment Plant, located at 5500 Heath Ln, Cambria, CA 93428, or mailed to Cambria Community Services District (CCSD) P.O. Box 65, Cambria, CA. 93428 by October 4, 2024, at 10:00 a.m. At 10:30 a.m. at 5500 Heath Ln, Cambria, CA 93428, said formal bids will be opened. Any bids which are delivered after this date and time will be refused. Any mailed bids received after this date and time will be returned unopened. Proposals that do not meet all the standards and requirements will not be considered.
Inquiries regarding this formal RFP should be directed to the Utility Manager via the Request for Information form on this page
Anticipated Schedule
Milestone | Date |
---|---|
RFP Issued | 9/12/2024 |
Recommended Pre-Bid Meeting | 9/30/2024 |
Deadline for Clarifications/Inquiries | 10/2/2024 |
Deadline to Submit Proposals | 10/4/2024 |
CCSD Selection of Contractor | 10/10/2024 |
Contract Negotiations | 10/10/2024 - 10/17/2024 |
Notice to Proceed | 10/21/2024 |
Construction Start Date, Phase 1 | 10/23/2024 |
Construction Completion Deadline, Phase 1 | 11/19/2024 |
Construction Start Date, Phase 2 | 1/28/2025 |
Construction Completion Deadline, Phase 2 | 2/28/2025 |
*Weather permitting.
**Anticipated.